General Contracting Services
Commercial Concrete Floors in Houston
Joint spacing decides how long a floor looks good, and subgrade decides whether it stays flat. Those two choices, made before a single truck of concrete arrives, explain most of what owners later call a good floor or a bad one. Slab-on-grade for a commercial or industrial building is a deceptively simple product with a long list of ways to go wrong: curling at the joints, random cracking, a surface that dusts under forklift traffic, or a flatness number that fails the racking vendor's tolerance.
We manage the placing and finishing of interior slabs for warehouses, distribution and fulfillment buildings, cold storage, manufacturing plants and large retail or flex space. The work includes subgrade preparation, vapor retarder, reinforcing or fiber, dowels at construction joints, placement by laser screed or manual screeding, power floating and troweling, curing, and saw cutting. Each of those steps has a time window set by temperature, humidity and mix design, and our job is to hit every one.
A floor is also the last structural element to be built before the shell is closed in and the racking arrives, so any slip upstream lands on it. We plan the pour calendar from the roof back, not from the slab forward.
Planning the pour before the dirt moves
The pour plan starts with the building's use. A fulfillment center with narrow-aisle trucks needs a superflat floor and tight joint control; a manufacturing bay with heavy machine pads needs thickened sections and embedded steel; a cold storage floor needs insulation, a heat source beneath the slab and careful vapor control. We ask for the racking layout, the forklift types and the equipment loads on day one, because those drive the slab thickness, the reinforcement and the finish tolerance.
With that information, we lay out placements in strips or checkerboard patterns, choose pour sizes the crew can finish before the set, and schedule the saw cutters so joints are cut within the narrow window after finishing. The ready-mix plant is part of the plan: batch times, truck spacing and reserve capacity all affect whether a slab is finished by dusk. We also decide in advance what happens if a truck breaks down or a storm arrives mid-pour, with a defined cold joint location and tools to cover the work.
Subgrade, steel and the surface
A slab is only as good as what lies beneath. Subgrade is trimmed to tolerance, proof-rolled and, on clay, often treated or capped with a granular base, and the moisture of the base is controlled before the vapor retarder and concrete go down. The work comes directly from the preceding mass grading and concrete foundations packages, and the earlier trades' tolerances either help or hurt us.
Placement uses laser-guided screeds on large floors for flatness, with bull floats, power floats and ride-on trowel machines bringing the surface up. Curing compound or wet curing starts right behind the finishers, and joints are sawn within hours. Hardeners or densifiers are applied where abrasion or dust is a concern. Afterwards the floor is measured for flatness and levelness, and any area outside tolerance is documented and addressed with grinding or an agreed remedy.
Tolerances, accessibility and the energy code
Commercial slabs are inspected by the city or the county, by special inspectors for reinforcement and concrete strength, and by the owner's own quality program. For energy, the state sets the energy code for commercial and industrial construction statewide, which bears on slab-edge insulation and on the insulated floors used in refrigerated space. Accessibility rules apply at entries, ramps and thresholds, and Texas Accessibility Standards registration and review applies to projects at or above $50,000.
Floor flatness specifications are set by the owner or the racking supplier, not by code, so the contract must state the target in measurable terms and the method of testing. We agree on those up front, and we propose test strips on large jobs where the specification is aggressive. A well-written specification protects everyone, and we prefer to negotiate it before the first pour than argue about it afterwards.
Where the money goes
Slab cost is driven by thickness, reinforcement type, flatness requirement and the size of the placement. Steel fiber can replace mesh or bars in some designs and speeds placement, but the engineer must agree to it. Polished or sealed concrete adds a grinding and finishing phase that costs more than a standard trowel finish but reduces maintenance. We show owners the base price and the options in separate lines so the trade-offs are visible.
Schedule also affects cost. A slab placed in July needs evaporation control and early-morning pours, while a winter slab needs protection from cold fronts. Sites at the Gulf Coast's industrial parks, such as the 232-acre Bay Area Business Park near the Bayport Container Terminal that delivered 1.3 million square feet of final speculative buildings in June 2020, show the scale at which repeating floor placements pay off: a crew that learns the building by the second bay is faster in the tenth. We price that learning curve honestly, and we do not promise savings that the site will not deliver.
Floors by building type
Distribution and fulfillment buildings are the largest consumers of floor area in the region. The West Houston Association reported that Grainger began a 1.2 million-square-foot distribution center in Hockley set to open in 2026, and that H-E-B broke ground on a 500-acre distribution campus in Hempstead. Floors of that size are a logistics exercise as much as a concrete one, and we describe our approach to them in more detail under distribution center and logistics and fulfillment work.
Pearland's Levey Logistics Park, a two-building, 662,000-square-foot development on 38 acres, was reported 100% leased in April 2026, including a lease of 496,560 square feet. Tenants of that size care about the floor in specific ways, from flatness for automated equipment to the abrasion resistance of dock-door aprons. Our logistics and distribution clients also ask about the transition at the dock, which links this work to truck courts and dock aprons.
Tell us the racking plan
Send the floor specification, the racking layout and the equipment loads. We will walk through pour sizes, joints and flatness targets and price the slab with options.
Common Questions
Why do slabs curl at the joints?
Concrete dries faster at the top than at the bottom, and the top shrinks more, lifting the corners. Joint spacing, mix design, curing and subgrade moisture all affect how much. We reduce curl with sound joint layout, early sawing and prompt curing.
What flatness number do we need?
It depends on the equipment. Narrow-aisle and automated systems need much tighter flatness than a wide-aisle storage building. Your racking or equipment vendor will specify a figure, and we build the plan around meeting it with a testing method everybody agrees on.
Can you pour in summer heat?
Yes, with controls. We schedule early-morning placements, use evaporation retarders, keep trucks moving and cure immediately. Hot-weather planning is routine on the Gulf Coast, and the mix design may be adjusted to extend working time.
What if a pour is interrupted by a storm?
We predefine the location of a cold joint and keep covers and pumps on hand. Whether to continue depends on the forecast, the concrete's set and the engineer's direction. We would rather end a pour early at a planned joint than finish badly in the rain.
When can racking go in after the pour?
Concrete reaches design strength over weeks, but racking and traffic can often begin sooner by agreement with the engineer, based on cylinder or beam test results. We confirm the release date with data and not with a guess.